A good architect is important. A good and daring one is necessary. Especially when the purchase has been more expensive than expected. You need an architect who knows how to maximise the scope of what you can do with the property. Enter Charlotte Morris Associates. Where other architects suggested designs for a smaller, less daring extension, and only on one level, we knew we had spent more than expected on the auction and therefore needed to maximise the renovation to go from 3 bed (2 double and 1 single) to 4 double bedroom plus study, large living/kitchen space.
From my last renovation, I had learnt that this was essential for market appeal especially given that the people who would likely be interested in this property in future would be families due to the large garden and proximity to primary school. So from then on, I endeavoured to view it through the eyes of a family. Easy for me to do, I have children myself. Charlotte Morris did too.
The application went without hitch. Charlotte was able to advise and guide me through questions. We received planning permission sometime in Nov 2022. The Building Regulations drawings and approval took another 2months. You need a structural engineer for this drawing because it is the one where a qualified person calculates the weight and distribution of support needed to ensure the building stays up and doesn't fall down..
In this instance, to illustrate, the building regulations drawing is like someone calculating the number of hidden dowels required in a tiered cake to ensure it stays upright for the duration of the wedding reception and where to position the said dowels. Whereas the architect drawing is like the cake designer sketching out how many tiers to make the cake, which shape to make the tiers etc.
Both aspects are essential and both require approval and each step took 4-8 weeks.

The Design

​

Existing front

Existing front

Proposed front

Proposed front

Existing rear

Existing rear

Proposed rear

Proposed rear

The Build

This began in March 2023 with Builder A. It was supposed to take 4 months, projected completion date: July 2023. What followed was a lesson in patience. After 6 months and stalled progress, we let go of builder A in September 2023 after a loss of nearly £40,000 in overpayments. 
We had Builder B begin in Sept 2023 and he was able to correct a lot of mistakes made by Builder A. New estimated completion date: Circa Feb 2024 
By Nov 2023, we hit a snag. That money lost with Builder A meant we had to source funds elsewhere. 
This caused delays.
It also meant that Builder B's tradesmen went off to work elsewhere. Good builders have to work to schedule
By the time we found funds 6 weeks later, these tradesmen were entrenched in work.
We waited over 3 months.
By May we were still very much behind.
It took another 3 months to do 3 weeks worth of work as the tradesmen tried to work whenever they had spare time.. which is almost never..
Still, I learned more patience...

Necessity births speed. Things move faster when you are onsite

Up till now,I'd project-managed from afar.
In October 2024, things changed. After 16 days living in a hotel, I was fast running out of money for hotels and moved into the property as below. I moved in on 27 October 2024 and that, which was not fun to say the least, really accelerated progress. I was able to find, assess tradesmen in person, say yay or nay and judge their work. I had to be precise in making judgement calls: My/my children's well being depended on it.
Click here to learn what I learnt
My bedroom (28/10/24)

My bedroom (28/10/24)

Bathroom 28/10/24 see things I learnt

Bathroom 28/10/24 see things I learnt

The "driveway" 28/10/24

The "driveway" 28/10/24

Driveway (28/10/24)

Driveway (28/10/24)

Back patio 28/10/24

Back patio 28/10/24

Driveway (7/11/24)

Driveway (7/11/24)

Persevere, it'll be rewarding. December 2024: